電纜溝工程項目承包合同
電纜溝工程項目承包合同
現今社會公眾的法律意識不斷增強,合同對我們的約束力越來越不可忽視,正常情況下,簽訂合同必須經過規定的方式。那么問題來了,到底應如何擬定合同呢?以下是小編收集整理的電纜溝工程項目承包合同,僅供參考,歡迎大家閱讀。
甲方(發包單位):Party A ( Employer )
乙方(承包單位):Party B (Contractor )
鑒于甲方與建設單位簽訂了工程建設總包合同,其中包括電纜溝施工項目需要專業施工分包人完成;
鑒于乙方系具有施工資質的工程建設單位,愿意依照招標文件所規定的質量要求分包電纜溝施工項目并完成;
為了按期完成合同段工程,經雙方協商,在遵守總合同的基礎上,根據《中華人民共和國民法典》和建設工程法律法規中的有關規定,由乙方承包本工程工程項目。
為明確雙方的權利、義務,特簽訂本合同,以共同遵守。
WHEREAS party A have, with the Owner, concluded the general contract of engineering construction which is inclusive of cable trench project needed professional constructor to complete;
WHEREAS party B is the qualified constructor, be willing, in accordance with the quality requirement of bidding documents, to subcontract and complete the project;
This Contract: For the purpose of accomplishment of the contracted engineering, parties hereto, through negotiation and on the basis of complying with the general contract, in accordance with LAW OF CONTRACT and relevant regulations of laws and rules on construction engineering, agree to award this project to party B for completion。
IN FAITH WHEREOF, to specify parties hereof ‘s rights and liabilities, make and enter into this contract hereby for abidance by parties。
一、工程概況及承包內容Project Overview and Contracting Works
1.1工程名稱及概況:工程名稱:電纜溝工程。本工程涉及三個變電站,分別是現有的220/35kV A472變電站、現有的35/10kV B301S變電站以及新建的35/10kV C581變電站。工作內容為三個變電站之間和從三個變電站接至MV用戶的電力電纜、控制電纜、接地電纜敷設所需電纜溝的開挖工程。
Name of Project and Overview: Name of Cable Trench;
The project involves three substations, namely the existing 220/35kV A472 substation, the existing 35/10kV B301S and a new 35/10kV C581 substation. Work contents are the excavation Works of trenches, between three substations and from the locations of three substations to MV user, which are necessary for laying out power cable, control cable, earth cable。
This is the power, control and grounding cable trench excavation project among three substations and for MV users connected to the three